Twenty Post Offices situated in Departmental Building of
LSG/Class-I status have been identified for “Look and Feel” activities under
Project Arrow Phase-VI during the financial year 2012-13. Fund has now been
allotted for Infrastructure / Branding activities in these 20 Departmental
Buildings. The time lines for the
completion of all activities as fixed by Directorate are as under:-
Activity
|
Time Line
|
Finalization of Tender / Award of Work
Order
|
02/11/2012
|
Completion of Civil Work /Electrical Work
and installation of hardware / software, branding activities and other
activities in at least 50% of Post Offices identified and booking of expenditure
|
30/11/2012
|
Completion of Civil Work /Electrical Work
and installation of hardware / software, branding activities and other
activities in rest of the Post Offices and booking of complete expenditure
|
31/12/2012
|
List of Identified
Post offices:
Sl.No
|
Region
|
Division
|
Name of the PO
|
Status of PO
|
Phase
|
Dept/Rented
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
|
1
|
Berhampur
|
Aska
|
Bellagunhta S.O
|
LSG
|
Phase-V
|
Departmental
|
|
2
|
Berhampur
|
Berhampur
|
Purusottampur S.O
|
LSG
|
Phase-V
|
Departmental
|
|
3
|
Berhampur
|
Kalahandi
|
Kesinga S.O
|
LSG
|
Phase-V
|
Departmental
|
|
4
|
Berhampur
|
Phulbani
|
Balliguda S.O
|
LSG
|
Phase-V
|
Departmental
|
|
Total
|
|||||||
1
|
Bhubaneswar HQ
|
Balasore
|
Baliapal S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
2
|
Bhubaneswar HQ
|
Bhadrak
|
Bant S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
3
|
Bhubaneswar HQ
|
Bhubaneswar
|
Kakatpur S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
4
|
Bhubaneswar HQ
|
Cuttack North
|
Binjharpur S.O
|
LSG
|
Phase-V
|
Departmental
|
|
5
|
Bhubaneswar HQ
|
Cuttack South
|
Balikuda S.O
|
LSG
|
Phase-V
|
Departmental
|
|
6
|
Bhubaneswar HQ
|
Cuttack South
|
Barambagarh S.O
|
LSG
|
Phase-V
|
Departmental
|
|
7
|
Bhubaneswar HQ
|
Cuttack South
|
Kujang S.O
|
LSG
|
Phase-V
|
Departmental
|
|
8
|
Bhubaneswar HQ
|
Cuttack South
|
Raghunathpur S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
9
|
Bhubaneswar HQ
|
Cuttack South
|
Tyandakura S.O
|
LSG
|
Phase-V
|
Departmental
|
|
10
|
Bhubaneswar HQ
|
Mayurbhanj
|
Udala S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
Total
|
|||||||
1
|
Sambalpur
|
Balangir
|
Binka S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
2
|
Sambalpur
|
Dhenkanal
|
Athamallik S.O
|
LSG
|
Phase-III
|
Departmental
|
|
3
|
Sambalpur
|
Keonjhar
|
Champua S.O
|
Class-I
|
Phase-V
|
Departmental
|
|
4
|
Sambalpur
|
Keonjhar
|
Joda S.O
|
LSG
|
Phase-V
|
Departmental
|
|
5
|
Sambalpur
|
Sambalpur
|
Rajborasamber S.O
|
LSG
|
Phase-V
|
Departmental
|
|
6
|
Sambalpur
|
Sundargarh
|
Biramitrapur S.O
|
LSG
|
Phase-V
|
Departmental
|